Below are the limitations of process flow in SLP
- It is not possible to send new questionnaires to the supplier in the middle of process.
Options: Standalone MQ, renew or cancel & restart
- The intake form can only be edited at the start and during Pending Decision phase.
If edited during Pending Decision, Matrix values are not editable. Only expiration, reminders & custom questions can be edited
- Process flow advanced view cannot be used to edit
• Intake form details
• Matrix information
• Setting predecessor
- Ability to configure predecessor or sequential tasks in the process template is not supported
- Field mapping other than Matrix Values and Expiry/Reminders are not supported in intake form. Field mappings cannot be used as conditions to trigger the MQ External Tasks in the process template.
- Cannot manage or deactivate Process level notifications
- Intake form doesn't have a version history
- Unlike MQs, Each Process template is mapped to process type 1:1. Every Process template must contain exactly one survey document (intake form) that users fill out to create projects from the template