Can I set up a task or phase to start automatically upon completion of a predecessor task?
Symptom

Issue in setting up task or phase after completion of Predecessor task


Resolution
Question

Can I set up a task or phase to start automatically upon completion of a predecessor task?

Answer

Yes, you can have a task or phase to start automatically upon completion of a predecessor task. This can be achieved using the task rule, Start When Dependencies Complete. This rule becomes available once you select a predecessor to the task.

You can enable this rule on a task by performing the following steps:

  1. Go to Tasks tab of the project, workspace or template where you would like a task to be started automatically
  2. Create a new task or edit an existing task you would like to start automatically
  3. Choose a task to populate the Predecessors field
  4. Click the checkbox to enable Start When Dependencies Complete
  5. Finish filling out the rest of the task details and click OK

For task automation to work correctly, you may have to consider the following two prerequisites:

Additional Information

This feature also introduces the below notifications which are sent when a phase or task is auto-started or cannot be auto-started by the system:

The templates for these notifications can be customized by site administrators within Manage > Administration > Project Manager > Project Email Templates.

You can find more additional documentation about self-starting tasks here.



Applies To

Strategic Contracts > Contract Tasks
Strategic Sourcing
Supplier Information & Performance Management

Terms of Use  |  Copyright  |  Security Disclosure  |  Privacy